The Worlds’ First 1240MW High-Efficiency Ultra-Supercritical Coal-Fired Power Plant Operated
Date:2020-08-14 VisitCount: Font size:[ L M S ]
In July, 2020, the Unit 5 and Unit 6 of Guangdong Huaxia Yangxi Power Plant were successively put into operation, engineered and built by Energy China, marking the completion of the world’s first 1240MW high-efficiency ultra-supercritical coal-fired project. The total installed capacity of the project is 2×1240MW. Energy China adopted the combined flue gas desulfurization and denitration technology in this project, by which its pollutants discharge has met the requirements of Ultra-Low Emission Standard. Meanwhile, Energy China has also used new technology about desulfurization wastewater treatment to achieve its Zero Liquid Discharge target.
 