On December 22, the IKN50 MW PV + 14 MW Energy Storage EPC project, undertaken by China Energy Construction Zhejiang Thermal Power, achieved full-capacity grid connection. This project is currently the largest energy storage project completed and commissioned in Indonesia. Located in Nusantara, the new capital of Indonesia, the project has a total installed DC capacity of approximately 70 MW, accompanied by a 20 MW/14 MWh energy storage system and a 150 kV substation, with a total construction area of about 70 hectares. It is primarily responsible for supplying power to the new capital region, including the new presidential palace and other facilities.