Local time on October 13, the boiler hydrostatic test at the Saraburi site of Thailand’s GULF Waste‑to‑Energy Project Group, which is EPC by China Energy Engineering Shanxi Electric Power Engineering Co., Ltd., was completed successfully on the first attempt. Major progress has been made in the project’s installation works, laying a solid foundation for subsequent boiler drying‑out, complete‑set commissioning and scheduled commissioning.

As a key milestone for verifying the installation quality of pressure‑bearing equipment, the boiler hydrostatic test saw the project team formulate scientific schemes, conduct collaborative tackling across multiple parties, and enforce strict whole‑process control over quality and safety. During the test, the equipment maintained stable pressure without leakage or abnormal deformation, and all indicators met relevant standards.
The Thailand GULF Waste‑to‑Energy Power Project serves as a demonstration project for China‑Thailand green energy cooperation. The overall project comprises twelve 9.9‑MW waste‑to‑energy power plants and three industrial solid‑waste treatment stations (with capacities of 750 tons, 1000 tons and 1250 tons respectively). The twelve project sites are distributed across five provinces in Thailand. Capable of efficiently realizing waste reduction, harmless treatment and resource utilization, the project will effectively improve local ecological environment, supplement clean power supply, and boost Thailand’s circular economy and low‑carbon development.