Road asphalt paving officially began on October 17 at Phase II of Kuwait's South Saad Al-Abdullah New City project. This milestone marks the start of Phase II's full construction, ushering the project into a new stage of full-scale construction.

The asphalt road network spans 23 districts across a total area of 64 square kilometers, with a combined road length of approximately 580 kilometers. The work involves laying 999,000 cubic meters of asphalt concrete, about 2.5 million metric tons, accounting for around 20% of the project's total construction value. Its substantial scale, high value, and complex coordination requirements make it a critical part of the project.
To address the challenges posed by the region's prolonged, extremely hot, and dry summers, the project team has optimized the asphalt concrete mix ratio design, along with mixing and paving procedures, to ensure compliance with all technical specifications. The team has also coordinated resource allocation and strengthened transitions across construction processes to manage simultaneous work across multiple districts and frequent overlaps between work areas. Strict safety and quality risk controls throughout the process have helped ensure efficient progress in paving operations.