Recently, with the completion of the final concrete pour, all roof slab pouring for the No. 1 Rainwater Tank of Package 1 of the Abdullah New City Project in Kuwait, constructed by Energy China CGGC, was completed and its main structure was officially topped out, laying a solid foundation for accelerating the project's subsequent construction across the board.

Covering an area of approximately 73,000 square meters with a net height of 6 meters and a design storage capacity of about 440,000 cubic meters, the No. 1 Rainwater Tank comprises 2,826 cast-in-place concrete columns and a total concrete volume of around 110,000 cubic meters. Currently the largest single rainwater tank in Kuwait, it serves as a critical node in the urban stormwater retention and drainage system of the project, playing an important role in ensuring smooth urban drainage, mitigating waterlogging risks during the rainy season, and creating and maintaining a safe and livable residential environment.

Since construction on the No. 1 Rainwater Tank commenced in January 2025, the project department has systematically formulated the construction schedule, centrally allocated diverse resources, and focused on overcoming technical challenges such as deep foundation pit operations, concrete pouring during hot seasons, and seepage and crack resistance through continuous process optimization and technical breakthroughs, ensuring first-pass high structural quality. Meanwhile, to address practical challenges including large concrete pour volumes, frequent concurrent operations, and tight construction schedules, the project department strengthened site management, refined the coordination between processes, and implemented section-based flow operations, ensuring continuous, efficient, safe, and orderly construction progress.